Case Studies : Westfield shopping town, Stratford
80,000 ft2 / 7,500 m2 to accommodate 250 office staff and 2,500 site operatives.
208 units of standard PremierPlus modular building system built
3 storeys high.
Building is on hire from Premier Interlink for 3 ½ years
From date of order received to complete handover = under 28 weeks. Includes off-site construction of buildings, site clearance and preparation, buildings to site and finishing/internal fitting out.
Total units on site – completed in record breaking 19 days!
Total project = 7 week accelerated programme (including 5 bad weather on site days!)
Ground floor canteen & welfare toilets
1st floor locker rooms - 2,500 lockers & showers
2nd floor offices & conference facilities
Handed over to client May 2008